Revocation of grants for floating thermal power plants in Rio de Janeiro increases expectations of NGOs regarding the definitive closure of the operation

The undertaking is the subject of judicial and administrative actions with the participation of the International Institute ARAYARA and the Observatório do Petróleo e Gás (OPG), due to the socio-environmental impacts on Sepetiba Bay, failure to submit an EIA-RIMA and non-compliance with the rules of the bidding notice

 

The decision by the National Electric Energy Agency (Aneel) to reinstate the revocation of authorization grants for the implementation and operation of Karpowership Brasil Energia’s floating thermal power plant complex, in Sepetiba Bay, in Rio de Janeiro, renewed the expectations of organizations of civil society regarding the possibility of the undertaking becoming unfeasible and definitively ending its operation, classified as high impact.

Since the launch of the public notice for the emergency contracting of these thermal plants, in October 2021, the Instituto Internacional ARAYARA, a member of the Coalizão Energia Limpa and the Observatório do Clima, as well as CONFREM, Instituto Boto Cinza and several doctors from the scientific community, have been pointing out inconsistencies in the contracting and licensing process for the complex that involves, in addition to four power plants (Karkey 13, Karkey 19, Porsud I and Porsud II), an LNG (liquefied natural gas) storage and regasification unit and 14 km of transmission lines, with 36 towers, installed in the sea, in mangroves and in an area of ​​Atlantic forest on the continent.

In the decision published last Thursday (2/16), the general director of Aneel, Sandoval de Araújo Feitosa Neto, argued that KPS has been demanding from the Electric Energy Trading Chamber (CCEE) the receipt of revenue from the sale of Energy Commercialization Contracts (CERs), but has avoided complying with public notice and contractual obligations, through administrative and judicial actions.

According to Aneel, the fines calculated by the CCEE for delays in energy delivery amount to R$ 843 million. The plants were supposed to start operating on May 1, 2022. KPS had already received BRL 394 million in January of this year, and the payment of another BRL 259 million in revenue was scheduled for this Friday (2/17 ). With the decision, payment is suspended.

“The judicial decisions ended up causing an unfavorable situation for consumers, by preventing the Electric Energy Trading Chamber – CCEE from applying the contractual fines related to the delay in the start of commercial operation of the plants until there is an administrative judgment of the exclusions of responsibility. In this way, the plant receives the contractual revenue, but fails to pay the fines it owes”, reported Sandoval Feitosa, in his dispatch.

For the Executive Director of ARAYARA.ORG, Dr. Nicole Oliveira, Aneel’s decision validates civil society’s efforts to defend a just energy transition and to avoid expanding the share of fossil fuels in the Brazilian electricity matrix. “We hope that Aneel’s next step, shortly, will be the definitive judgment of the request for exclusion of responsibility made by KPS, already denied at first , so that the company is effectively held responsible and penalized for non-compliance with the contracts”, said Nicole .

“An important decision by Aneel’s board, which values ​​the energy consumer by ensuring that the contract is fulfilled. The thermal plants were contracted at very high prices and were not delivered on time. Contracts and probable environmental and climate damage are other important points to be reviewed by the current Brazilian energy policy”, added the technical director of the Observatório do Petróleo e Gás (OPG) and ARAYARA, Dr. Eng. Juliano Bueno de Araujo.

Compartilhe

Share on whatsapp
WhatsApp
Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

Enviar Comentário

O seu endereço de e-mail não será publicado. Campos obrigatórios são marcados com *

Redes Sociais

Posts Recentes

Receba as atualizações mais recentes

Faça parte da nossa rede

Sem spam, notificações apenas sobre novidades, campanhas, atualizações.

Leia também

Posts relacionados

ARAYARA na Mídia: Sem licença ambiental, UTE São Paulo, de 1,7 GW, fica fora do leilão capacidade

O projeto da usina termelétrica (UTE) São Paulo, da Natural Energia, não conseguiu licença prévia e ficará fora do leilão de reserva de capacidade que deve ocorrer em junho deste ano. O prazo para cadastramento e envio de documentos para a participação no certame se encerrou na última sexta-feira, 14 de fevereiro. O projeto da UTE São Paulo prevê instalação

Leia Mais »

 Leilão de Capacidade de 2025: UTE São Paulo ficará de fora, após despacho do IBAMA   

A Usina Termelétrica (UTE) São Paulo, empreendimento da Natural Energia, não  poderá participar do Leilão de Reserva de Capacidade de 2025, devido à ausência da Licença Prévia (LP), um dos requisitos para habilitação no certame. O Instituto Brasileiro do Meio Ambiente e dos Recursos Naturais Renováveis (IBAMA), apontou que os estudos apresentados até o momento pela empresa não atenderam integralmente

Leia Mais »

ARAYARA na Mídia: Geradora avança em licenciamento de térmica que seria beneficiada com derrubada de vetos no Congresso Nacional

Projeto prevê a conexão da UTE Brasília, de 1.470 MW, ao gasoduto Brasil Central, da TGBC BRASÍLIA e RIO — A Termo Norte Energia, geradora que tem como sócio o empresário Carlos Suarez, conseguiu marcar a audiência pública para construção de uma térmica em Brasília (DF), onde não há suprimento de gás natural. O projeto estima um consumo de 5,80 milhões de

Leia Mais »

ARAYARA na Mídia: Petrobras inicia obras, treina agentes e fala de ‘otimismo’ para explorar petróleo na Amazônia

Licença depende do Ibama, sem prazo para ser liberada. Servidores do instituto reclamam de “pressão” para concluir documento Em meio ao impasse enfrentado pelo governo de Luiz Inácio Lula da Silva sobre explorar petróleo na Margem Equatorial, a Petrobras aposta em obras da unidade de estabilização e despetrolização de fauna em Oiapoque, município localizado no Amapá e prospectado como a capital nacional do

Leia Mais »